| BILL OF QUANTITIES FOR THE BUDDHA STATUE IN WALKING STANCE at Sri Sumangala Piriven Rajamaha Viharaya, Wariyapola, Sri Lanka (Stage - I) | ||||||||||
| Item | Description of works | Qty. | Unit | Rate | Amount | |||||
| no. | Rs | Rs | ||||||||
| 1.0 | Dowelling | |||||||||
| 1.1 | Geo-technical investigation with two boreholes drilling up to 10m depth in the rock and | Item | Allow | Sum | 172,500.00 | |||||
| core sampling of the rock profile and opinion for foundation design work. | ||||||||||
| 1.2 | Blasting of rock for preparation surface to receive base foundation in hexagonal shape | Item | Allow | Sum | 224,040.00 | |||||
| approximate depth 2'-6" | ||||||||||
| 1.3 | 20mm Tor steel bar vibrated in to hole filled with cement sand (1:3) | |||||||||
| mortar with non shrink addive. (Bar length - 7'-1") | 40.00 | Nos | 4,969.50 | 198,780.00 | ||||||
| Sub Total | 595,320.00 | |||||||||
| 2.0 | R/R Masonry Work | |||||||||
| 2.1 | Random rubble (6"x9") masonry in cement mortar 1:5 in retaining wall | 12.63 | m3 | 7,200.00 | 90,936.00 | |||||
| 2.2 | 3/4" thick D.P.C in cement sand 1:2 finished with two coats of D.P.C | |||||||||
| tar and blinded with sans | 6.33 | m2 | 500.00 | 3,165.00 | ||||||
| Sub Total | 94,101.00 | |||||||||
| 3.0 | Concrete | |||||||||
| Grade 35A concrete for base foundation. The quality of the concrete should be confirm | ||||||||||
| to the ICTAD specification for building works. | ||||||||||
| 3.1 | Concrete for Leveling of existing excavated rock surface | 22.00 | m3 | 12,400.00 | 272,800.00 | |||||
| 3.2 | Concreting of Base - 1 | 99.00 | m3 | 12,400.00 | 1,227,600.00 | |||||
| 3.3 | Concreting of Base - 2 | 35.00 | m3 | 12,400.00 | 434,000.00 | |||||
| 3.4 | Concreting of Base - 3 | 14.24 | m3 | 12,400.00 | 176,576.00 | |||||
| 3.5 | Partition walls and circular columns | 5.76 | m3 | 12,400.00 | 71,424.00 | |||||
| 3.6 | 2" thick screed concrete (GR 10) for column bases | 2.17 | m2 | 12,400.00 | 26,908.00 | |||||
| 3.7 | Grade 35A concrete for column bases (F1 columns) | 0.55 | m3 | 12,400.00 | 6,820.00 | |||||
| 3.8 | Grade 35A concrete for columns(C1 columns) | 2.02 | m3 | 12,400.00 | 25,048.00 | |||||
| 3.9 | Grade 35A concrete for Beams (B-1) | 1.57 | m3 | 12,400.00 | 19,468.00 | |||||
| 3.10 | Grade 35A concrete for Beams (B-2) | 3.27 | m3 | 12,400.00 | 40,548.00 | |||||
| 3.11 | 12" Thick top slab for statue base | 8.76 | m3 | 12,400.00 | 108,624.00 | |||||
| 3.12 | 8" Thick continuation slab | 7.39 | m3 | 12,400.00 | 91,636.00 | |||||
| Sub Total | 2,501,452.00 | |||||||||
| 4.0 | Form Work | |||||||||
| Form work in approved timber props, joints and planks rate to include for splayed edges' | ||||||||||
| battens , stuttering , bolting , welding, easing, removal | ||||||||||
| 4.1 | Shuttering for sides of foundation including dismantling - Base 1 | 23.23 | m2 | 1,200.00 | 27,876.00 | |||||
| 4.2 | Shuttering for sides of foundation including dismantling - Base 2 | 27.78 | m2 | 1,200.00 | 33,336.00 | |||||
| 4.3 | Shuttering for sides of foundation including dismantling - Base 3 | 18.58 | m2 | 1,200.00 | 22,296.00 | |||||
| 4.4 | Shuttering for sides partition walls and circular columns including dismantling | 51.28 | m2 | 1,200.00 | 61,536.00 | |||||
| 4.5 | Shuttering for columns including dismantling - Column F 1 | 3.10 | m2 | 1,200.00 | 3,720.00 | |||||
| 4.6 | Shuttering for columns including dismantling - Column C1 | 8.83 | m3 | 1,200.00 | 10,596.00 | |||||
| 4.7 | Shuttering for columns including dismantling - Beam B1 | 8.75 | m3 | 1,200.00 | 10,500.00 | |||||
| 4.8 | Shuttering of slab including dismantling | 18.69 | m3 | 1,200.00 | 22,428.00 | |||||
| Sub Total | 192,288.00 | |||||||||
| 5.0 | Reinforcement Steel | |||||||||
| Steel bar reinforcement cut to length , bent to shape place in position as reinforcement | ||||||||||
| to RCC work. Rate shall include for binding wires hangers,chairs,spacer block etc. | ||||||||||
| Tor steel reinforcement slabs, beams, lintels, columns, footings ect.bent to shape, | ||||||||||
| laid in position and tied with blinding wire | ||||||||||
| 5.1 | 20mm Dowel bars for base | 0.21 | Tons | 162,000.00 | 34,020.00 | |||||
| Base - 1 | ||||||||||
| 5.2 | 25mm reinforcement for Bottom and secondary bars for base foundation | 6.43 | Tons | 162,000.00 | 1,041,660.00 | |||||
| 5.3 | 16mm reinforcement for top and main distribution, perimeter and stools | 2.05 | Tons | 162,000.00 | 332,100.00 | |||||
| Base - 2 | ||||||||||
| 5.4 | 25mm reinforcement for top, distribution and stools | 4.04 | Tons | 162,000.00 | 654,480.00 | |||||
| 5.5 | 12mm reinforcement for perimeter area | 0.14 | Tons | 162,000.00 | 22,680.00 | |||||
| Base - 3 | ||||||||||
| 5.6 | 32mm Tor steel reinforcement for top main, distribution and stools | 5.93 | Tons | 162,000.00 | 960,660.00 | |||||
| 5.7 | 10mm steel reinforcement for circular columns. | 1.44 | Tons | 162,000.00 | 233,280.00 | |||||
| 5.8 | 6mm steel reinforcement for stirrups | 0.02 | Tons | 162,000.00 | 3,240.00 | |||||
| 5.9 | 12mm steel reinforcement for new columns | 0.18 | Tons | 162,000.00 | 29,160.00 | |||||
| 5.10 | 10mm steel reinforcement for new columns | 0.07 | Tons | 162,000.00 | 11,340.00 | |||||
| 5.11 | 6mm steel reinforcement for new column stirrups | 0.04 | Tons | 162,000.00 | 6,480.00 | |||||
| 5.12 | 16mm steel reinforcement for Beam B1 | 0.22 | Tons | 162,000.00 | 35,640.00 | |||||
| 5.13 | 6mm steel reinforcement for Beam B1 | 0.04 | Tons | 162,000.00 | 6,480.00 | |||||
| 5.14 | 16mm steel reinforcement for Beam B2 | 0.17 | Tons | 162,000.00 | 27,540.00 | |||||
| 5.15 | 12mm steel reinforcement for Beam B2 | 0.09 | Tons | 162,000.00 | 14,580.00 | |||||
| 5.16 | 6mm steel reinforcement for Beam B2 | 0.07 | Tons | 162,000.00 | 11,340.00 | |||||
| 5.17 | 32mm steel reinforcement for 4'x4' void area wall | 2.67 | Tons | 162,000.00 | 432,540.00 | |||||
| 5.18 | 10mm steel reinforcement for 4'x4' void area wall | 0.23 | Tons | 162,000.00 | 37,260.00 | |||||
| 5.19 | 16mm steel reinforcement for statue base slab | 0.37 | Tons | 162,000.00 | 59,940.00 | |||||
| 5.20 | 10mm steel reinforcement for statue base slab | 1.33 | Tons | 162,000.00 | 215,460.00 | |||||
| 5.21 | 12mm steel reinforcement for lotus petals | 0.08 | Tons | 162,000.00 | 12,960.00 | |||||
| 5.22 | 10mm steel reinforcement for lotus petals | 0.21 | Tons | 162,000.00 | 34,020.00 | |||||
| 5.23 | 10mm steel reinforcement for edge beam | 0.14 | Tons | 162,000.00 | 22,680.00 | |||||
| Sub Total | 4,239,540.00 | |||||||||
| 6.00 | Structural Steel | |||||||||
| 6.10 | 400x400x172mm UC section grade 43A (18-'3" x 4) with 16mm thk steel base plate | 22.25 | lm | 35,245.00 | 784,201.25 | |||||
| (18" x 18") | ||||||||||
| 6.12 | Transporting, Fabricating, Welding and placing of UC sections | Item | Allow | Sum | 46,250.00 | |||||
| Sub Total | 830,451.25 | |||||||||
| S U M M A R Y COST ESTIMATE FOR STAGE - I | ||||||||||
| 1.00 | Dowelling | 595,320.00 | ||||||||
| 2.00 | R/R Masonry Work | 94,101.00 | ||||||||
| 3.00 | Form Work | 192,288.00 | ||||||||
| 4.00 | Concrete | 2,501,452.00 | ||||||||
| 5.00 | Reinforcement | 4,239,540.00 | ||||||||
| 6.00 | Steel | 830,451.25 | ||||||||
| TOTAL COST FOR STAGE - I | 8,453,152.25 | |||||||||